Programme

The structures were craned into position using a 300te grove.  The bridges were uniform in finish.  A 36m,  an 18.7m and a 5m structure all constructed in steel and timber, with a hardwood finish.  All steelwork was coated with HA Type II Alternative Paint System,  FSC hardwood all fixings galvanised.

Environmental and ecology factors were carefully managed throughout the duration of these works, eg. the presence of otters, bats and newts had to be considered within our programme and dealt with in the proper way.

All criteria were met, on time and performed safely.