From concept to completion, Beaver Bridges offers end-to-end services for permanent and temporary bridge projects. Whether you're planning new infrastructure or upgrading existing assets, our in-house teams deliver compliant, cost-effective, and future-ready solutions — on time, every time.
From national infrastructure to private developments, Beaver Bridges supports a wide range of sectors with bespoke bridging solutions. Our experience spans highways, rail, energy, and public sector projects — as well as private estates and commercial schemes. Wherever your project sits, we have the tools, talent, and track record to deliver.
Explore the wide range of bridge solutions delivered by Beaver Bridges. We design and build both permanent and temporary structures for projects of all sizes. With strong engineering expertise and a practical approach, we provide safe, reliable and compliant bridge systems tailored to each project’s needs and environment.
From remote landscapes to live rail environments, Beaver Bridges thrives in complex settings where others hesitate. Our in-house team brings together decades of engineering expertise, ensuring we meet challenges head-on — safely, sustainably, and without compromise.
The scheme consists of the ‘fabrication’ of a replacement stressed laminate timber arch off site. Partial demolition of the existing structure to remove the existing arch and re-erection using the replacement. The timber for the arch was procured in its raw state, cut by a Computer Numerically Controlled processor, and treated. These laminates were used to fabricate the replacement arch in Beaver Bridges Workshop, on a specially designed scaffold temporary works. The profile of the arch at all stages compared to a Point Cloud survey carried out during the initial stages. Additional temporary works will be installed once the arch is complete, bracing the arch for transport and installation. This load forms an abnormal load and will be handled by Beaver Bridges in house transport.
Beaver bridges intend to carry out the partial demolition and reassembly of the structure during a 48-hour road closure utilising a 100t crane. Temporary propping to the existing arch will be erected in advance of the closure and within traffic management to allow for the method of demolition.
The replacement arch will be lifted, in one large section direct from the transport with the temporary bracing removed once installed. All lifting planning and supervision will be carried out in house by Beaver Bridge Specialists.
Parapet repairs and surfacing after the install should see this bridge back in action my mid-March 2021.