From concept to completion, Beaver Bridges offers end-to-end services for permanent and temporary bridge projects. Whether you're planning new infrastructure or upgrading existing assets, our in-house teams deliver compliant, cost-effective, and future-ready solutions — on time, every time.
From national infrastructure to private developments, Beaver Bridges supports a wide range of sectors with bespoke bridging solutions. Our experience spans highways, rail, energy, and public sector projects — as well as private estates and commercial schemes. Wherever your project sits, we have the tools, talent, and track record to deliver.
Explore the wide range of bridge solutions delivered by Beaver Bridges. We design and build both permanent and temporary structures for projects of all sizes. With strong engineering expertise and a practical approach, we provide safe, reliable and compliant bridge systems tailored to each project’s needs and environment.
From remote landscapes to live rail environments, Beaver Bridges thrives in complex settings where others hesitate. Our in-house team brings together decades of engineering expertise, ensuring we meet challenges head-on — safely, sustainably, and without compromise.
The project included the removal of an existing structure, Cat II design check, expert bridge design and the installation of new foundations. We were also tasked with designing, building and installing a new vehicle bridge, with 44te loading over 6-axles and designed and built with pedestrian walkways. The finished bridge was a steel structure with C24 timber pedestrian parapet restraint. The deck was finished with a resin bonded aggregate, non-slip surface and an HA Type II Alternative Paint System.
A new residential housing development was in its second stage when we were contacted by the client. They hired Beaver Bridges, as a subcontractor, to remove an existing structure and provide bridge design and the installation of new foundations, based on GI data provided by the Client.
Beaver Bridges also provided the client with the design, build and instalment of a new vehicle bridge with pedestrian walkways which linked completed phase one to phase two which was underway. The already populated phase one meant that access to the site of the bridge was tight. A crane was situated on the developed side and slung across the brook, thus joining it to phase two. A large tree stump had to be removed from the finished side of the development to prepare for the new mass concrete foundations. Works on site began in December 2016 with the removal element and the project was completed in January 2017. All men, plant, machinery and RAMs supplied by Beaver Bridges Ltd, with a CPA Crane Hire.
All works were completed with safely, without any health & safety issues, with minimum disruption to residents and with sensitivity to the local environment.